Bloomberg:美国数据中心自建电站 90GW 落地仅 2GW
数据中心等电网接入动辄要等几年,于是开发商自己建电站,但 90GW 计划里只有 2GW 真转起来了。成本比电网贵 10 美元每兆瓦时,备份和负载波动都是硬伤。关注 AI 算力扩容和电力瓶颈的人该看看这篇。
Bloomberg 报道,开发商为美国数据中心宣布的自建电站(behind-the-meter)规模约 90GW,但目前真正运行的只有约 2GW,占比约 2%。
技术上,自建电站难以替代电网:电网靠多座电厂和线路互为备份,单座现场电厂一旦故障就没有后备;AI 负载在几秒内的需求波动足以损坏部分现场发电设备。若用太阳能加电池让一座 100MW 的德州数据中心达到 98% 的时间可用,需要将近 1,800 公顷土地。
成本上,开发商因此多建燃气机组,每兆瓦时成本超过 100 美元,而电网电价约 90 美元。大多数开发商把自建电站当作电网接入前的过渡方案,而非长期主力。
Bloomberg: Self-powered data centers ("behind-the-meter") are mostly still plans:
developers have announced about 90GW of their own power plants for US data centers ("behind-the-meter"), but only about 2GW of that, around 2%, actually runs so far.
The grid keeps power flowing when one machine fails because it draws on many plants and lines, while a single on-site plant has no such backup. AI workloads also swing demand within seconds, enough to damage some on-site generators, and solar plus batteries would need almost 1,800 hectares to run a 100MW Texas data center just 98% of the year.
So developers build extra gas capacity, pay over $100 per megawatt-hour against about $90 for grid power, and mostly treat their own plants as a bridge until the grid connection arrives.