TrendForce:高端GPU交货周期延长5周至45周,NVIDIA Rubin切换期开始

精选理由

买GPU的朋友注意了,TrendForce说高端卡交货周期涨到45周,NVIDIA Rubin切换期云厂商先拿货,企业得继续等。

TrendForce数据显示,高端GPU交货周期从40周延长5周至45周,原因是NVIDIA开始向Rubin平台过渡。超大规模云厂商预计率先拿到Rubin,企业买家将继续停留在现有GPU平台。内存方面,96GB和128GB RDIMM供应有所改善,但32GB和64GB模组依然紧张;DRAM交货周期缩短1周至19周,仍是正常水平的两倍多。由于服务器要等最慢的部件到货才能出货,Rubin量产爬坡取决于基板和电容——这两类部件交货周期已超过均衡水平的3倍。

原文 · rohanpaul_ai

TrendForce: Top-end GPU lead times jumped 5 weeks to 45 as NVIDIA’s Rubin transition begins.

Hyperscalers will likely get NVIDIA’s Rubin first, leaving enterprise buyers on existing GPU platforms.

96GB and 128GB RDIMMs are arriving faster, but 32GB and 64GB modules remain severely tight.

DRAM lead times eased 1 week to 19, yet still run more than double normal.

Since a server ships only when its slowest part arrives, Rubin’s ramp depends on substrates and capacitors running more than 3 times their balanced lead times.